UQD02–08 · second-source programmes
Second source, same test gate
Spec-first components for CDU and liquid cooling programmes.
Request the OEM qualification packHow you would test us
Three gates · before any market number
Gate 1 · ΔP
25–150%
pressure drop measured across that share of rated flow, at documented flow points rather than at one point. industry-published benchmark
Gate 2 · cross-mating
Interchange
plugs and sockets of a second source have to mate with parts already in service. That interchange is the precondition, not the bonus.
Gate 3 · reports
Clause map
the report is mapped to specification clauses one by one. A single pass mark on the cover is not a result.
Looks identical, fails the test. That is the risk a second-source programme is set up to close. And the reason this screen comes before the market story.
The shape of the market
Two published views · kept separate
Two research houses, two shapes of one curve. Plan capacity against the band, not against a single point.
Supply
UQD supply is concentrated in the hands of a few suppliers. That concentration is where the interchange requirement comes from, not from us. industry-published benchmark
A second source is judged on the parts it can put beside the first source's parts: same size family, same bore ladder, same interface.
Who carries the fluid risk
Reference fluids · compound level · change control
Spec reference fluids
DOWFROST LC 25 and JEFFCOOL ISF-25, the two inhibited propylene-glycol reference fluids named in the specification, of the PG25 class. They are named in the standard as its compatibility baseline; naming them here is a technical reference, not a partnership. per the OCP UQD specification
Seal compound level
Compatibility is verified compound by compound: EPDM, FFKM and the rest. It is not asserted for a material family as a whole. industry practice
Change control
Replacing a seal compound requires the compatibility work to be redone and the file updated. A swap without that re-verification is not offered. process capability
Fluid compatibility is a programme, not a statement about a material. Ask for it by compound and by fluid, and keep the answer on file with the batch.
What a programme receives
Curve data · traceability · cross-mating · benchmark
Cv / ΔP curve
Documented curve data at the flow points, so the selection and the flow budget are read off the same sheet. industry practice
Lot traceability
Traceability at batch level, so a programme audit can be answered at your site rather than in a summary. process capability
Cross-mating
Cross-mating test records travel with the batch they belong to. process capability
Benchmark discipline
The top of this market helium-tests every coupling and publishes a flow figure 25% above the OCP community standard. It is quoted here as the bar, not as our number. industry benchmark
Files for the destination market
Per market · version watch · pack contents
Qualification files are read by two different departments, engineering and sourcing. The pack is built to answer both without a second round of questions.
OEM qualification pack
Which gate does your programme start at?
Tell us which of the three gates your qualification starts with and we return the matching pack. Capacity planning here is done against the 19.0% CAGR curve (industry-published benchmark), not against a single published point.